The Insulation Guy (S & S Industrial Insulation) provided an energy survey of the entire steam system, including supply and return piping, valves, heat exchangers, and equipment. The entire project required five months to complete. By investing $70,000 in labor and materials for the project, the company that contracted the insulation provider saw a return of 200 percent in reduced energy costs.
Materials totaling 30,878 ft. of mostly uninsulated steam return and 10% steam supply | $28,000 |
Labor | $42,000 |
Total Materials and Labor | $70,000 |
Anticipated Annual Energy Savings | $140,000 |
Payback — one heating season | 5 months |
Return on Investment | 200% |
Cost of Natural Gas | $7.20 per MSF |